Home is where the heart is
Unveil our new home 3 @ Sandilands
After months of cover up with canvas, 3@Sandilands unveil for the first time end of October.
3@Sandilands Unveil as 31 Oct 09
Unblocked view of 3@Sandilands after removal of canvas.
3@Sandilands as 24 Oct 2009
Interior is almost done as 24 Oct
Front view of 3@Sandilands as 31 Oct
3@Sandilands from diaganol view as 31 Oct
3@Sandilands TOP soon as 31 Oct
November 8, 2009 Site visit update. Balcony fitting completed. Air-con ledge completed
3Sandilands as 8 Nov
.
3@Sandilands update as 8 Nov
Niangzi infront of 3@Sandilands as 8 Nov
3@Sandilands Carpark Work in Progress as 8 Nov
November 14, 2009
NiangZi infront of 3@Sandilands as 14 Nov
3@Sandilands front gate work in progress as 14 Nov
No much progress visible from external view of 3@Sandilands 14 Nov
.
.
| Print article | This entry was posted by xianggong on November 15, 2009 at 10:08 pm, and is filed under Property, Singapore, Weblogs. Follow any responses to this post through RSS 2.0. You can leave a response or trackback from your own site. |



about 7 months ago
Any idea when is TOP of 3@Sanilands?
about 7 months ago
Alex,
3@Sandilands should be TOP very soon. My last visit last week already done up the carpark, swimming pools and most of the landscaping completed.
I guest should be in the early January, more or less the same timing as Resorts World Sentosa opening.
KC
about 6 months ago
Hi, thank you for all the pictures & update @ Sandilands. Have you when into your unit to see already? We went last week & was quite disappointed as the workmanship was not very good. Also, can see our neighbors’ laundry & kitchen from our poolside.
about 6 months ago
Yes. I noticed that since last month too. I will log this as defect as fence downgrade the value of the pool and add value to our neighbors.
about 6 months ago
Hi, any idea when top?ya i got a studio unit.
about 6 months ago
Not ready yet. I went there last Sunday. Notice the worker there working on the rubbish chute opening in kitchen.
I have called developer last week. They mentioned the construction work completed waiting for Architect to certify and TOP approval. No date was given.
Why don’t u give them a call as well? Tel: 62388446
about 5 months ago
Hello, nice to come across this blog. We bought #04-03.
Just called the developer, no commitment on TOP date, but he expects it to be very soon (2-3 wks).
about 5 months ago
Hi Royston,
2-3 week is very soon. Any idea on how long it take from TOP to hand over the keys?
Thanks for the update and stopping by our blog.
about 5 months ago
Yes… 3@Sandilands already TOP !!!!

Plan Reference No: A1631-00323-2007-BP01
Application Type: BCA-TOP-APPLN
Current Status: APPROVED
Current Status Date / Time: 02/03/2010 10:19:54
Registration Date / Time: 26/01/2010 08:30:00
about 4 months ago
Checked with the developer at 62388446 today and the lady in charge seems to be unaware of the TOP on 2/3/10, says they are still waiting for confirmation from architects.
about 4 months ago
Call the developer, they say they are sorting out the paper works, should send us the letter in 3 weeks or so.
about 3 months ago
Did you notice that the number of carpark spaces are less than the 22, stated in the contract?
about 3 months ago
I did not noticed the number of carpark in the contract. What I know is 1 lot per unit so should be 20 lots.
There are 20 lots plus 1 visitor lot.